Recommended Commissioning Procedure - Part Ii: Software - Siemens SIMATIC S7-300 Hardware And Installation Manual

Hide thumbs Also See for SIMATIC S7-300:
Table of Contents

Advertisement

Recommended procedure - Part II: Software
Table 9-2

Recommended commissioning procedure - part II: software

Tasks
Switch on the PG
and start SIMATIC
Manager
Download the
configuration and the
program to the CPU
Testing the I/Os
Commission PROFIBUS
DP or other networks
Connect the outputs
Danger
Proceed step-by-step. Do not go to the next step unless you have verified the
previous one without error/error message.
response to errors
React to errors as follows:
• Check the system with the help of the Checklist in the chapter below.
• Check the LED displays on all modules. Notes on their significance can be
found in the chapters describing the relevant modules.
• If required, remove individual components to trace the error.
Important notes are also found ...
in Chapter Testing Functions, diagnostics and fault elimination
see also
The commissioning checklist
S7-300 Programmable Controller Hardware and Installation
A5E00105492-02
Remarks
-
Helpful functions are here:
Monitoring and controlling of variables
Testing with program status
Force
Controlling outputs in Stop mode (PA
isolation)
Tip: Test the signals at the inputs and outputs
using the simulation module SM 374, for
example.
-
Commissioning the outputs successively.
[ → Page 9-4]
Commissioning
Information can be
found in ...
in the STEP 7
Programming Manual
in the STEP 7
Programming Manual
in Chapter Testing
Functions, Diagnostics
and Fault Elimination
in Chapter Commissioning
PROFIBUS DP
-
9-3

Advertisement

Table of Contents
loading

Table of Contents