8
Installation and commissioning
After the machine has been unpacked, check it for any damages caused during transportati-
on. If there are any damages, please notify the transport company and your
local PFAFF agency.
8
Installation
.01
Suitable connections for electricity and compressed air must be available at the machine's lo-
cation (see Chapter 3 Specifications). An even and firm foundation as well as sufficient
lighting must also be available at the machine's location.
8
Setting up the PFAFF 8310-041/001 and the PFAFF 8310-041/002
.01.01
5
Fig. 8 - 01
Slide the machine off the pallet.
●
Turn the six legs 1 to level the machine horizontally.
●
Connect the plugs from pedal 2 and from any existing foot switches to the control box.
●
Loosen screws 3 and 4 and adjust the height of the machine by turning crank 5.
●
Well tighten screws 3 and 4 again.
●
The machine must only be installed and commissioned by qualified personnel.
All relevant safety regulations must be strictly adhered to!
4
4
Installation and commissioning
4
3
4
1
2
19