4 SETUP AND PROCEDURE BEFORE STARTING THE OPERATION
4.2 Procedure Before Starting the Operation
The figure below shows the steps that should be followed before starting the
QD62(E/D) operation.
Module mounting
Mount the QD62(E/D) in the specified slot.
Wiring
Wire external devices to the QD62(E/D).
Intelligent function module switch setting
Perform settings using the GX Developer
(see Section 4.5)
Use the GX Configurator-CT?
Initial setting
Using the FROM/TO commands, create
a sequence program for writing initial values.
Programming
Create and check a counter processing
program using the FROM/TO commands.
4 - 2
Start
Yes
No
Operation
Initial setting
Perform the initial setting using the GX
Configurator-CT (see Section 7.4).
Perform automatic
No
refresh setting?
Yes
Automatic refresh setting
Perform the automatic refresh setting
using the GX Configurator-CT
(see Section 7.5).
Programming
Create and check a counter processing
program without using the FROM/TO commands.
MELSEC-Q
4
4 - 2