PROCEDURES BEFORE OPERATION

4.1
Procedures Before Operation
Consideration of system configuration
Complete the following items prior to the module installation.
1.
Determine a safety category required for configuring the safety system.
2.
Determine function wiring required for configuring the safety system.
3.
Determine the network number and station number of the safety remote I/O module.
Module installation, wiring, and parameter setting
1.
Mounting the module
Mount the safety remote I/O module on the panel surface or a DIN rail. When using an extension module, connect the
extension module to the safety remote I/O module and mount the safety remote I/O module on the DIN rail.
Page 51 Connecting extension modules
Page 54 Mounting the module on a DIN rail
2.
Wiring to the power supply module
Connect the safety remote I/O module to the module power supply and the external power supply.
Page 57 Wiring of terminal block for module power supply and FG
Page 63 Wiring of terminal block for the external power supply and I/O signals
3.
Unit test
Wire the module, set the unit test in the station number switch setting, and perform the unit test of the safety remote I/O
module.
Page 126 Unit Test
4.
Station number setting
Set station numbers of the safety remote I/O module using the station number setting switch.
Page 48 Station number setting with the station number setting switch
5.
Wiring
Connect the Ethernet cable and external devices to the safety remote I/O module.
Page 60 Wiring of Ethernet cable
Page 63 Wiring of terminal block for the external power supply and I/O signals
6.
Powering on the safety remote I/O module
Stop the CPU module and turn on the module power supply and the external power supply of the safety remote I/O module.
7.
Parameter setting
Set the module parameters of the master module and the safety remote I/O module in the engineering tool.
Page 68 VARIOUS SETTINGS
8.
Checking the entire system
According to the manuals of the CPU module and the master module, check the entire system for wiring, the station number
switch setting, and others.
9.
Safety remote I/O module validation
Enable the module parameters of the safety remote I/O module.
Page 78 Parameter Settings
10.
Starting the system
Change the status of the CPU module to RUN.
11.
Starting the system operation
4 PROCEDURES BEFORE OPERATION
4.1 Procedures Before Operation