2.3
Quick commissioning
The following descriptions show how to set up the drive using the quick commissioning wizard
integrated in the BOP-2.
Starting quick commissioning
• Press ESC to enter the menu selection.
• Use the UP and DOWN buttons to move the menu cursor to the word "Setup" and press OK.
• The screen will automatically display the next parameter in the commissioning sequence.
Quick commissioning begins now. It leads you step by step from parameter to parameter.
Parameters that are not relevant will be skipped automatically. Essentially, you are adjusting
the factory settings of your inverter to the requirements of your motor.
Reset inverter
• Reset the inverter to factory state by first pressing OK while the BOP-2 shows RESET.
• Press UP or DOWN to change the value to YES.
• Press OK and wait until BUSY sign disappears (approx. five seconds).
Operator Panels BOP-2 and IOP:
24
ESC
OK
OK
Quick commisioning
OK
OK
Don't forget: switch on the
power supply before initial
start-up.
Note