PROGRAM DEVELOPMENT PLAN
ACTIVITY TIME ESTIMATES
"Must"
Original Schedule
Revised
Revised
Duration
Start (S) or
Dates*
Dates # 1*
Dates
# 2*
in
Finish (F)
Activity
Weeks
Date
Start
Finish
Start
Finish
Start
Finish
Define PAY 01 (Payroll)
.1
Flowchart PAY 01
.1
Code PAY 01
.1
Desk-check, list PAY 01
.1
Test data PAY 01
.1
Test PAY 01
.2
Production test PAY 01
.2
Complete documentation PAY 01
.2
Define PAY 02 (Payroll)
1.0
Flowchart PA Y 02
.5
Code PAY 02
.8
Desk-check, list PAY 02
.2
Test data PAY 02
.2
Test PAY 02
1.0
Production test PAY 02
1.0
Complete documentation PAY 02
.5
Define PAY 03 (Payroll)
.5
Flowchart PAY 03
.2
Code PAY 03
.5
Desk-check, list PA Y 03
.1
Test data PAY 03
.1
Test PAY 03
.2
Production test PAY 03
.2
Complete docu mentation PAY 03
.2
Define PAY 04 (Payroll)
.5
Flowchart PAY 04
.2
Code PAY 04
.5
Desk-check, list PAY 04
.1
Test data PAY 04
.2
Test PAY 04
.2
Production test PAY 04
.2
Complete documentation PAY 04
.2
Define PAY 05 (Payroll)
.5
Flowchart PAY 05
.2
Code PAY 05
.5
Desk-check, list PAY 05
.1
Test data PAY 05
.2
Test PAY 05
.2
Production test PAY 05
.2
Complete documentation PAY 05
.2
Define PAY 06 (Payroll)
.5
Flowchart PA Y 06
.2
Code PAY 06
.5
Desk-check, list PAY 06
.1
Test data PAY 06
.2
Test PAY 06
.2
Production test PAY 06
.2
Complete documentation PA Y 06
.2
Define PAY 07 (Payroll)
.5
Flowchart PAY 07
.2
Code PAY 07
.5
Desk-check, list PAY 07
.1
Test data PAY 07
.2
Test PAY 07
.2
Production test PAY 07
.2
Complete documentation PA Y 07
.2
*Only one start and finish date should be supplied for each program being developed.
Figure 05.8 (Sheet 1 of 5).