SmartNode 4400 Series Getting Started Guide
F • Installation checklist

Introduction

This appendix lists the tasks for installing a SmartNode 4400 IpChannel Bank (see
table
12). Make a copy of
this checklist and mark the entries as you complete each task. For each IpChannel Bank, include a copy of the
completed checklist in your site log.
Table 12. Installation checklist
Task
Verified by
Date
Network information available & recorded in site log
Environmental specifications verified
Site power voltages verified
Installation site pre-power check completed
Required tools available
Additional equipment available
All printed documents available
SmartWare release & build number verified
Rack, desktop, or wall mounting of chassis completed
Initial electrical connections established
ASCII terminal attached to console port
Cable length limits verified
Initial configuration performed
Initial operation verified