Installation Of The Panel; Mains Connection - Kemppi mastertig mls 2300 acdc Operation Instruction Manual

Hide thumbs Also See for mastertig mls 2300 acdc:
Table of Contents

Advertisement

Installing gas-cooled torch

2.5. INSTALLATION OF THE PANEL

1. Fasten the cable connectors of the function panel to the power source (2 pieces).
2. Place the bottom edge of the panel behind the securing clips on the machine. Remove the
fixing pin from the top edge with, for example, a screwdriver. Then gently push the upper
part of the panel into place. Make sure that the cables do not get damaged, continue gently
pushing the upper part of the panel until it clips into place. Finally, push the fixing pin back
into its place.

2.6. mAINS CONNECTION

Only an authorised electrician is allowed to install mains cable and plug!
The machine comes equipped with a three-metre power cord with a Schuko plug. Only an authorised
electrician is allowed to replace the plug. The fuse and cable sizes are given in the Technical data
at the end of this manual.
This equipment's electromagnetic compatibility (EMC) is designed for use in an
industrial environment. Class A equipment is not intended for use in residential location
where the electrical power is provided by the public low-voltage supply system.
© keMppi oy
Installing water-cooled torch
1.
Torch
2.
Mastertig MLs™ 300 aDCD / 0743 – 7

Hide quick links:

Advertisement

Table of Contents