Figure 15-28 Remote Operator Interface - Mainframe Cable Connection
WARNING!
The cables should be routed in accordance with local codes. This includes areas free of
debris and liquids and away from sharp edges or objects that can pinch or cut the cable
housing or conductors. The cables should not be bent at a radius less than 4x the outer
diameter of the cables. Ensure that the cables are routed in areas where the ambient
temperature is within a range of -10 °C to 60 °C (14 °F to 140 °F). It is also recommended
that the cables are routed away from other cables, especially those that are high
voltage or high frequency, to minimize signal interference.
7.
Figure 15-29 Remote Operator Interface - Route Cables
8.
Install the Remote Operator Interface
Route the 7.6 m (25 ft) Communication and Power cables from the controller mainframe
to the location of the operator interface. Refer to
Connect the male end of the 7.6 m (25 ft) communication cable to the female
communication connector on the bottom of the operator interface MCU. Refer to
v 1.0 — February 2020
Figure
15-29.
Maintenance
219