Diagnostic Mode for 25‐CB120 Scrolling Board 
To enter Diagnostic Mode, the unit must be off and completely shut down. 
 Press the UP , DOWN and ON buttons simultaneously, and release. 
 The unit will scroll "DIAGNOSTIC MODE" followed by "REV 3.1", for example (or whatever revision is 
present on the board at the time).  
o NOTE: If the board is not loaded with a "PRO" file to operate the unit, the display will show 
"REV 3.0", and will need to be uploaded with this file to operate properly. 
 Press the ON button. 
o The board will flash the LED's of the display. This is to test that all LED's are functional. 
 Press the ON button. 
o The board will scroll "AUGER OFF" at this point. To test the auger motor, press the UP arrow. 
The board will then scroll "AUGER ON" and the auger motor should run continuously. To stop 
the auger, press the DOWN arrow, and the board will revert to scrolling "AUGER OFF" and the 
motor will stop. (It is recommended the burn pot be installed during this portion of the test to 
prevent pellets from dropping into the cradle below the burn pot). 
 Press the ON button. 
o The board will scroll "DRAFT OFF" at this point. To test the draft (exhaust) blower, press the UP 
arrow. The board will then scroll" DRAFT ON" and the draft blower will run at its highest output. 
To stop the draft blower, press the DOWN arrow, and the board will revert to scrolling "DRAFT 
OFF" and the blower will stop.  
o NOTE: the draft blower must be running to test the vacuum circuit later in the test, so, to leave 
it running, simply leave the board in the "DRAFT ON" configuration.  Do not press the DOWN 
arrow; instead press ON button to skip to the next step leaving the draft blower running. 
 Having pressed the ON button: 
o The board will scroll "ROOM AIR OFF" at this point. To test the room air (convection) blower, 
press the UP arrow.  The board will scroll "ROOM AIR ON" and the room air blower will start 
running at its highest output. To stop the room air blower, press the DOWN arrow, and the 
board will revert to scrolling "ROOM AIR OFF" and the blower will stop. 
 Press the ON button. 
o The board will scroll "IGNITER OFF". To test the igniter, press the UP arrow. The board will then 
scroll "IGNITER ON" and the ignitor will energize and begin to heat up. After 3 to 4 minutes, the 
igniter should be at its full temperature and the glow from it should be visible in the mouth of 
the ignitor tube (it is recommended that the burn pot be removed during this part of the test 
(USE CAUTION AND NECESSARY PROTECTIVE GLOVES, GEAR, ETC.), especially if the burn pot 
has fuel in it from testing the auger. Also, the draft blower is running to pull air through the 
ignitor sleeve if all steps above were followed). To power down the igniter, press the DOWN 
arrow.  The board will revert to scrolling "IGNITER OFF" and the ignitor will power down. 
IMPORTANT!  READ AND FOLLOW ALL INSTALLATION AND MAINTENANCE INSTRUCTIONS, INCLUDING CLEANING THE UNIT AS SPECIFIED, AND 
ENGLAND'S STOVE WORKS IS NOT RESPONSIBLE FOR ANY DAMAGE OR INJURY INCURRED DUE TO NEGLECT, OR DUE TO UNSAFE INSTALLATION OR 
 
 
REPLACING GASKETS ANNUALLY, AND PARTS AS NEEDED. 
USAGE OF THIS PRODUCT. CALL TECHNICAL SUPPORT WITH ANY QUESTIONS. 