Underfloor Heating Screed Dryout - Daikin ERLA11D V3 Series Installer's Reference Manual

Hide thumbs Also See for ERLA11D V3 Series:
Table of Contents

Advertisement

12
|
Commissioning

12.4.5 Underfloor heating screed dryout

About underfloor heating screed dryout
Installer reference guide
246
2 Go to [A.2]: Commissioning > Actuator test run.
3 Select a test from the list. Example: Pump.
4 Select OK to confirm.
Result: The actuator test run starts. It stops automatically when
ready (±30 min).
To stop the test run manually:
1 In the menu, go to Stop test run.
2 Select OK to confirm.
Possible actuator test runs
Backup heater 1 test
Backup heater 2 test
Pump test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
Shut off valve test
Diverter valve test (3-way valve for switching between space heating and
tank heating)
Bivalent signal test
Alarm output test
C/H signal test
DHW pump test
Bizone kit direct pump test (bizone kit EKMIKPOA or EKMIKPHA)
Bizone kit mixed pump test (bizone kit EKMIKPOA or EKMIKPHA)
Bizone kit mixing valve test (bizone kit EKMIKPOA or EKMIKPHA)
Purpose
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
NOTICE
The installer is responsible for:
contacting the screed manufacturer for the maximum allowed water
temperature, to avoid cracking the screed,
programming the underfloor heating screed dryout schedule according to the
initial heating instructions of the screed manufacturer,
checking the proper functioning of the setup on a regular basis,
performing the correct program complying with the type of the used screed.
ERLA11~16D + EBVH/X11+16S18+23D
Daikin Altherma 3 R F
4P643602-1B – 2022.05