Figure 35: Open Baskets
c. Gather the SAS, power, and Ethernet cables for installation.
d. Route all of the cables being connected to the enclosure through the open baskets.
e. Close all of the baskets.
f. If the Ultrastar Serv60+8 is being installed in a rack and will subsequently be transported
inside that rack, it is important to use the included cable tie to wrap the CMA bundle to
ensure it does not get damaged during transport. If the Ultrastar Serv60+8 is instead being
installed where it will operated, skip this step. Remember to remove the cable ties after the
enclosure has reached its final operational location.
g. Reconnect the arm to the rail by the connector at the elbow.
Step 2 : Make sure the CMA(s) is in operational position by folding the arm(s) in toward the enclosure and
attaching the elbow end(s) to the connector(s) attached to the rail. Verify that all of the cabling is
in functional order and does not bind or catch.
Step 3 : Test for binding in the extension of the arm by gently pulling the enclosure out of the rack,
ensuring the cables extend properly and that the system doesn't bind at all. If it does, examine
the point at which the binding occurred and adjust the seating of cables in the baskets, check
the connections to the rails, and examine the joints of the arm to ensure that they are all
functioning properly.
Note: Route all cables to IOM A (left hand side looking at the rear).