Titan 165/ 110 Technical Service Manual

2.0 Calibrations

D o not w ear ties, loose fit clothing or
dangling jew elry w hile operating or
servicing the lam inator. T hese item s can get
caught in the nip and choke you or you can
be crushed or burned.
O nly the prim ary person ( person
perform ing the calibration ) m ay control the
functions of the lam intor during any
calibration procedure!
Calibrations ensure the optimal performance of
the machine during operation. All procedures in this section
should only be performed by a qualified service technician
( Qualified is described in Section 1 ).
The following procedures are described in this
section; Main roller nip, Pull roller nip, Clutch tensioning
and Temperature calibration.
A lw ays exercise extrem e caution w hen
perform ing calibration procedures.
C abinets, panels and covers m ust be
rem oved and pow er to the m achine is O N .
© GBC Films Group October 2000
W AR N IN G
C AU T IO N
E L E C T R IC AL
S H O C K

2.1 Main roller nip

This calibration ensures the main rollers nip is even
from left to right. Main roller nip should be performed at
time of installation.
Tools required
• Two rolls of thermal film ( see film width below )
T110 = 41 in. rolls / T165 = 51 in. rolls
• 2.5 mm allen wrench
• 3 mm allen wrench
• 5 mm allen wrench
• # 2 phillips screwdriver
• Small flat tip screwdriver
A lw ays practice lock out/ tag out procedures
w hen perform ing service related w ork.
a) Set up he machine as you would for two sided
thermal encapsulation.
b) After webbing the machine, run about 1 ft. of
material through and then stop for about 30
seconds.
c) After aproximately 30 seconds, run the web out
until the nip impression in the laminate exceeds
the pull rollers by 1 ft.