Test

Perform the tests always:
after installation
after every system maintenance action
after a change in settings (dip switches or rotary switches)
periodically according to the local requirements
(local standards and/or safety rules)
WARNING!
Test procedure:
1. Test the OFF behaviour. See § 3.1 on page 8
2. Test the ON behaviour.
3. Log the test results.
Incorrect testing can cause potentially hazardous situations
which, if not avoided, could result in death or serious injury.
Additionally, there may be severe property damage.
See § 3.2 on page 9
See Appendix B: Logging of test results on page 77