Procedure
Step 1.
Touch the static-protective package that contains the hot-swap power supply to any unpainted
surface on the outside of the server. Then, take the hot-swap power supply out of the package and
place it on a static-protective surface.
Step 2.
If there is a power-supply filler installed, remove it.
Figure 85. Hot-swap power supply filler removal
Step 3.
Slide the new hot-swap power supply into the bay until it snaps into position.
Figure 86. Hot-swap power supply installation
After you finish
1. Connect one end of the power cord to the new power supply connector; then, connect the other end of
the power cord into a properly grounded electrical outlet.
2. If you have adjusted the CMA to gain access to the power supply bay, properly readjust the CMA back
in place.