Preparation - Siemens Simotics M-1FE1 Series Hardware Installation Manual

Synchronous built-in motors for sinamics s120
Hide thumbs Also See for Simotics M-1FE1 Series:
Table of Contents

Advertisement

Mechanical mounting
5.3 Mounting/dismantling the rotor
5.3.2

Preparation

Perform the following work before starting mounting:
1. Check that the components to be joined are correct and complete.
2. Clean the surfaces to be joined as a prerequisite for the separation and reuse of the
components later. The surfaces to be joined must be free from contamination, rust, sharp
edges, damage and machining marks.
3. Clean the oil connection holes in accordance with the following description.
– Remove the grub screws from the connection holes.
– Remove oil, grease or other contaminants from the grub screws and holes (e.g. with
4. Measure and record the radial runout of the spindle to the reference plane, see
measurement plane "R"
R
Y
A-B
Figure 5-5
60
Loctite 7061 or 7063).
Note
Observe the manufacturer's instructions for the cleaning products used.
Ensure adequate ventilation for solvent-based products.
Spindle shaft
Position of the rotor core
Oiled surface (mounting without stress relief)
Reference plane for radial runout check
Measured value (before and after mounting)
Spindle shaft axis (reference axis)
Checking the radial runout
1FE1 synchronous built-in motors
Hardware Installation Manual, 12/2016, 610.43000.40b