Starting the vacuum pump, when the indicator turns to-1 bar, closing the low pressure handle
and stopping vacuumize. Keep for 15 minutes, ensuring the pressure of the vacuum watch
remains.
Take out the valve cover of the gas valve together with the liquid valve.
Loosing the cord of liquid valve until the pressure rise to 0 bar.
Dismantle the tube from the cover of the inlet for refrigerant then, tighten the cover.
Loose the valve cord of the gas valve as well as the liquid valve entirely.
Tighten the valve cover of the gas valve and liquid valve so as to check whether leakage
occurred.
3) Installation of Protective Layer of Connecting Pipe
To avoid generation of condensate on the connecting pipe and avoid leakage, the big pipe and
the small pipe of the connecting pipe must be covered by thermal insulation materials, be
bundled by adhesive tape, and be isolated from air.
The joint connecting to the indoor unit must be wrapped by thermal insulation material.
There shall be no gap between the connecting pipe joint and the wall of the indoor unit. Refer
to Figure 3-1-6.
Figure 3-1-5
Figure 3-1-6
INSTALLATION
Figure 3-1-7