Dismantling the Boiler
To ensure the continued safe and efficient operation of the
appliance, it is recommended that it is checked and serviced
as necessary at regular intervals.
The frequency of servicing will depend upon the particular
installation conditions and usage but in general once per
year should be adequate. It is the law that all servicing work
is carried out by a competent person such as British Gas or
other CORGI registered personnel.
Before servicing please read the Important Information
section on page 5.
After servicing, complete the relevant section of the
"Benchmark" Installation, Commissioning and Service
Record Log Book. This should be in the possession of the
user.
ISOLATE THE ELECTRICAL SUPPLY TO THE BOILER.
Remove lower door panel following the sequence of
diagrams.
To remove the outer case from the boiler, take out the two
screws and washers. Draw outer case forward and clear of
the boiler.
1. Turn off gas supply at the service tap and disconnect the
union.
2. Disconnect the electrical plug on the gas valve by
removing screw and pulling forward.
3. Disconnect the two wires from the overheat thermostat.
4. Loosen the screw on the capillary retaining washer,
allowing the washer to move freely. Release the capillaries
from the clips on the side of the combustion box. Remove
both phials from the thermostat pocket.
5. Remove brass sealing plug with fibre washer.
6. Loosen the six screws sufficiently for the removal of the
combustion chamber door.
Remove the combustion chamber door complete with the
burner.
NOTE: When re-assembling, care must be taken to align
the overheat thermostat capillary with the groove in the main
thermostat phial.