Baxi Solo 3 Installation And Servicing Instructions page 23

Baxi solo 3 pfl system, wall mounted powered flue system boiler, gas fired central heating unit
Table of Contents

Advertisement

6.0 Installation
6.10
Method A (Cont)
7. Engage the assembly into the hole previously
cut in the wall and slide into place (Fig. 50).
8. Secure the assembly to the wall at the
previously drilled anchorage points with suitable
screws. Before finally tightening the screws,
check that the assembly is level.
9. Make good between the wall and the air duct
inside and outside the building if the internal fitting
kit has not been used (Fig. 51).
Fig. 50
10. The flue trim provided may be fitted if
required, to neaten up the make-up around the
terminal (Fig. 52).
11. To fit the flue terminal trim:
a) The trim should be fitted once the flue is
secure.
b) Take the three edge clips from the kit and fit
them equi-spaced onto the inner flange of the trim
(Fig. 51a).
c) With the flanges towards the wall pass the trim
over the terminal. If required a bead of sealant
may be applied to the rear face of the trim.
Fig. 51
d) Push firmly on the trim to ensure the edge clips
Edge Clip
engage on the flue.
Flue Trim
Fig. 51a
Fig. 52
Flue Trim
23