MACHINE INSTALLATION

UNCRATING MACHINE

1. Carefully check shipping crate for signs of
damage. Report damages at once to carrier.
2. To uncrate the machine, remove the shipping
hardware and straps that secure the machine to
the pallet. Use the attached ramp and carefully
back the machine off the pallet. Make sure the
scrub head is in the raised position.
ATTENTION: Use the supplied ramp when
uncrating the machine to prevent machine
damage.
3. Check the contents list, contact the distributor if
an item is missing.
Contents:
Machine
D
2 Extractor Brushes
D
2 ReadySpace Rollers
D
1 Extractor Vacuum Shoe
D
2 ReadySpace Vacuum Shoes (installed)
D
Vacuum Shoe Removal Tool
D
2 Scrub Head Flush Lines (installed)
D
Scrub Head Vacuum Tube (Installed)
D
Battery Tray (installed)
D
Operator Training CD--ROM (English)
D
Battery Kit (Option)
D
Battery Charger (Option)
D

INSTALLING BATTERIES

WARNING: Fire Or Explosion Hazard.
Batteries Emit Hydrogen Gas. Keep Sparks And
Open Flame Away. Keep Battery Hood Open When
Charging.
FOR SAFETY: When servicing machine, wear
protective gloves and eye protection when
handling batteries and battery cables. Avoid
contact with battery acid.
Battery Specifications:
Four 6 volt deep cycle lead acid batteries.
180AH/5H Semi Traction Batteries
165AH/5H Maintenance Free Batteries
175AH/5H Traction Batteries
Maximum battery dimensions: 181 mm W x 260 mm L
x 292 mm H.
1. Park the machine on a level surface, remove the
key and set the parking brake.
8
Home
Find... Go To..
2. Lift the recovery tank to access the battery
compartment (Figure 1).
FIG. 1
3. Carefully install the batteries into the battery
compartment tray and arrange the battery posts
as shown (Figure 2).
4
BLACK
5
RED
Connect wire #47 from machine's wire
harness.
FIG. 2
4. Before connecting the battery cables, make sure
the terminals and posts are clean. Use a post
cleaner and wire brush if necessary.
NOTE: Apply a light coating of non-metallic grease or
protective spray on the cable connections to prevent
battery corrosion.
5. Connect the cables to the battery posts in
numerical order as labeled (Figure 2), RED TO
POSITIVE & BLACK TO NEGATIVE.
6. After installing the batteries, check the battery
meter charge level. The machine must be in full
operation for an accurate reading (See MACHINE
OPERATION). Charge batteries if needed.
3
2
1
Tennant 1610 (10- -05)

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents