Chapter 4: Cabling the Network Ports

Installing Optional Transceivers

Installing an SFP
Transceiver
76
Review the following guidelines before installing an optional SFP or XFP
transceiver in a switch:
A transceiver can be hot-swapped; the switch can be powered on
when you install it. However, you should always disconnect the cables
first before removing a transceiver.
You must install the transceiver before you connect the cables to it.
Fiber optic transceivers are dust sensitive. When a fiber optic cable is
not installed, or when you store the transceiver, always keep the plug
in the optical bores. When you do remove the plug, keep it for future
use.
Unnecessary removal and insertion of a transceiver can lead to
premature failure.
The SFP slots on some AT-9400 Switches are paired with twisted pair
ports. For operational information, refer to "Redundant Twisted Pair
Ports" on page 26.
Warning
A transceiver can be damaged by static electricity. Be sure to
observe all standard electrostatic discharge (ESD) precautions,
such as wearing an antistatic wrist strap, to avoid damaging the
device.
To install an SFP transceiver in the AT-9424Ts or AT-9424Ts/XP Switch,
perform the following procedure:
1. Remove the dust plug from a transceiver slot on the switch, as shown
in Figure 31.
Figure 31. Removing a Dust Plug for an SFP Slot

Advertisement

Table of Contents
loading

This manual is also suitable for:

At-9424tsAt-9448ts/xpAt-9424ts/xpT-9424ts