5.10.1 Installing Gas Bottle - Kemppi Kempoweld WIRE 400 Operating Manual

Hide thumbs Also See for Kempoweld WIRE 400:
Table of Contents

Advertisement

5.10.1 installing gas bottle

Always fasten gas bottle properly in vertical position in a special holder on the wall or on a
NOTE!
carriage. Remember to close gas bottle valve after having finished welding.
parts of gas flow regulator
A.
Gas bottle valve
B.
Press regulation screw
C.
Connecting nut
D.
Hose spindle
E.
Jacket nut
F.
Gas bottle pressure meter
EN
G.
Gas hose pressure meter
The following installing instructions are valid for most of the gas flow regulator types:
1.
Step aside and open the bottle valve (A) for a while to blow out possible impurities from
the bottle valve.
2.
Turn the press regulation screw (B) of the regulator until no spring pressure can be felt.
3.
Close needle valve, if there is one in the regulator.
4.
Install the regulator on bottle valve and tighten connecting nut (C) with a wrench.
5.
Install hose spindle (D) and jacket nut (E) into gas hose and tighten with hose clamp.
6.
Connect the hose with the regulator and the other end with the wire feed unit. Tighten
the jacket nut.
7.
Open bottle valve slowly. Gas bottle pressure meter (F) shows the bottle pressure.
Do not use the whole contents of the bottle. The bottle should be filled when the bottle
NOTE!
pressure is 2 bar.
8.
Open needle valve if there is one in the regulator.
9.
Turn regulation screw (B) until hose pressure meter (G) shows the required flow (or
pressure). When regulating flow amount, the power source should be in switched on and
the gun switch pressed simultaniously.
Close bottle valve after having finished welding. If the machine will be out of use for a long
time, unscrew the pressure regulation screw.