CONTINUED FRAMING AND INSTALLATION
CONSTRUCTION
FRAMING
3. The 80ZC cabinet exterior roof or chase framing as follows:
47 1/2"
NOTE: No floor protector or finished hearth is needed directly under the Model 80ZC Cabinet, only the
hearth protector is needed.
WARNING:
Install the hearth protector or finished hearth extension only as specified. The exten-
sion must extend a minimum of 16" in front of the stove door opening and must be 47 1/2" wide mini-
mum. Refer to (Page 6) for calculation of R, and K values.
CORNER LOCATION
FIGURE 19
CHIMNEY CAP
STROM COLLAR
ROOF FLASHING
2" X 4" STUDDING
CHIMNEY PIPE
METAL FIRE STOP
USE FIRE CODE SHEET ROCK
2" X 4" STUDDING
A SINGLE HEADER MUST BE INSTALLED ABOVE CABI-
NET. VERTICAL 2" X 4"'s MUST BE TURNED FLAT.
41 1/2"
NOTE: FINISHED WALL MUST BE 2 1/2" IN FRONT OF FACE
OF ZC CABINET (WITHOUT HOOD TRIM ATTACHED).
NOTE: A DOUBLE HEADER MUST BE USED ON A LOAD
BEARING WALL.