Gas Connections - Modine Manufacturing PDP Installation And Service Manual

Pdp/bdp series power vented gas-fired unit heaters
Hide thumbs Also See for PDP:
Table of Contents

Advertisement

InsTAllATIon

gAs ConneCTIons

WARNING
1. All field gas piping must be pressure/leak tested prior to
operation. Never use an open flame. Use a soap solution
or equivalent for testing.
2. Gas pressure to appliance controls must never exceed
14" W.C. (1/2 psi).
3. To reduce the opportunity for condensation, the minimum
sea level input to the appliance, as indicated on the serial
plate, must not be less than 5% below the rated input, or 5%
below the minimum rated input of dual rated units.
CAUTION
1. Purging of air from gas lines should be performed as
described in the National Fuel Gas Code, ANSI Z223.1
(NFPA 54) - latest edition or in Canada CSA-B149 codes.
2. When leak testing the gas supply piping system, the
appliance and its combination gas control must be
isolated during any pressure testing in excess of
14" W.C. (1/2 psi).
3. The unit should be isolated from the gas supply piping
system by closing its field installed manual shut-off valve.
This manual shut-off valve should be located within 6' of
the heater.
4. Turn off all gas before installing appliance.
IMPORTANT
To prevent premature heat exchanger failure, the input to
the appliance, as indicated on the serial plate, must not
exceed the rated input by more than 5%.
1. Installation of piping must conform with local building codes,
or in the absence of local codes, with the National Fuel Gas
Code, ANSI Z223.1 (NFPA 54) - Latest Edition. In Canada,
installation must be in accordance with CSA-B149.1.
2. Piping to units should conform with local and national
requirements for type and volume of gas handled, and
pressure drop allowed in the line. Refer to Table 10.1 to
determine the cubic feet per hour (cfh) for the type of gas
and size of unit to be installed. Using this cfh value and
the length of pipe necessary, determine the pipe diameter
from Table 10.2. Where several units are served by the
same main, the total capacity, cfh and length of main must
be considered. Avoid pipe sizes smaller than 1/2". Table
10.1 allows for a 0.3" W.C. pressure drop in the supply
pressure from the building main to the unit. The inlet
pressure to the unit must be 6-7" W.C. for natural gas and
11-14" W.C. for propane gas. When sizing the inlet gas
pipe diameter, make sure that the unit supply pressure
can be met after the 0.3" W.C. has been subtracted. If the
0.3" W.C. pressure drop is too high, refer to the Gas
Engineer's Handbook for other gas pipe capacities.
3. Install a ground joint union with brass seat and a manual
shut-off valve adjacent to the unit for emergency shut-off
and easy servicing of controls, including a 1/8" NPT
plugged tapping accessible for test gauge connection
(see Figure 10.1).
4. Provide a sediment trap before each unit and in the line
where low spots cannot be avoided (see Figure 10.1).
5. When Pressure/Leak testing, pressures above 14" W.C.
(1/2 psi), close the field installed shut-off valve, disconnect
the appliance and its combination gas control from the
gas supply line, and plug the supply line before testing.
When testing pressures 14" W.C. (1/2 psi) or below, close
the manual shut-off valve on the appliance before testing.
10
figure 10.1 - recommended sediment Trap/manual
shut-off valve Installation for gas Connection
SUPPLY LINE
GAS
SUPPLY LINE
3"
MIN.
SEDIMENT
Manual shut-off valve is in the "OFF" position when handle is perpendicular
to pipe.
Table 10.1 - manifold Pressure & gas Consumption ➀
manifold Pressure
model size
("W.C.)
150
Gal/Hr. Propane
Orifice Drill Size
175
Gal/Hr. Propane
Orifice Drill Size
200
Gal/Hr. Propane
Orifice Drill Size
250
Gal/Hr. Propane
Orifice Drill Size
300
Gal/Hr. Propane
Orifice Drill Size
350
Gal/Hr. Propane
Orifice Drill Size
400
Gal/Hr. Propane
Orifice Drill Size
Table 10.2 - gas Pipe Capacities - natural gas
Pipe
length (ft)
1/2"
3/4"
10
132
278
20
92
190
30
73
152
40
63
130
50
56
115
60
50
105
70
46
96
80
43
90
100
38
79
125
34
72
150
31
64
Capacities in Cubic Feet per Hour through Schedule 40 pipe with maximum
0.3"W.C. pressure drop with up to 14"W.C. gas pressure. Specific gravity is 0.60
for Natural gas and 1.50 for Propane gas.
For Pipe Capacity with Propane Gas, divide Natural gas capacity by 1.6. Example:
What is the propane gas pipe capacity for 60' of 1-1/4" pipe? The Natural gas
capacity is 400 CFH. Divide by 1.6 to get 250 CFH for Propane gas.
6-580.7
GAS
GROUND
JOINT
UNION
W/ BRASS
SEAT
MANUAL GAS
SHUT-OFF VALVE
TO
CONTROLS
PLUGGED
1/8" NPT TEST
GAGE CONNECTION
TRAP
natural
Propane
3.5
10
CFH
138.1
58.0
-
1.64
21
39
CFH
166.7
70.0
-
1.86
28
43
CFH
190.5
80.0
-
2.19
25
42
CFH
238.1
100.0
-
2.74
18
36
CFH
285.7
120.0
-
3.29
21
39
CFH
333.3
140.0
-
3.84
23
41
CFH
381.0
160.0
-
4.38
25
42
natural gas
1"
1-1/4" 1-1/2"
520
1050
1600
3050
350
730
1100
2100
285
590
890
1650
245
500
760
1450
215
440
670
1270
195
400
610
1150
180
370
560
1050
170
350
530
930
150
305
460
870
130
275
410
780
120
250
380
710
# of
orifices
2
3
3
3
4
5
6
➀ ➁
2"

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PDP and is the answer not in the manual?

Questions and answers

Table of Contents

Save PDF