10.1

Unpacking

Unpack the UPS indoors on a paved floor. The UPS should be as close as possible to its final storage
location. Overhead traveling cranes should be used to unpack any G8000 Series UPS. If an overhead
traveling crane is not available, allow enough space for forklift operations to unpack the UPS crate. Then
remove the crate.
Points to observe
Retain all small articles during unpacking and installation.
Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.
DO NOT damage the UPS when using tools to remove packaging materials.
If provided, DO NOT remove the plastic sheet cover, until installation.
Do not remove the fan covers until UPS start up. The fan covers should be removed by factory
authorized personnel. Packing materials should be disposed by the appropriate means.
Immediately report any abnormalities to Toshiba Customer Support Center or an authorized
representative.
10.2

UPS Clearance

Maintain the indicated clearance during installation. See Figure 10.1. Ensure that the front and top air vents
are NOT blocked.
Side 0 in. (0 mm)
28
Top 16 in. (400 mm)
Front
44 in.
(1100 mm)
FIGURE 10.1 - UPS CLEARANCE
G8000 Series Installation and Operation Manual
Back 0 in. (0 mm)