Installing the Switches in an Equipment Rack

Perform the following procedure to install each switch in a standard
19-inch rack:
Note
Steps 1, 2, and 3 are optional. These steps provide instructions on
how to remove the snap-on plastic feet from the bottom of a switch.
You can leave the feet on.
1. Place the switch upside down on a level, secure surface.
2. Using a flat-head screwdriver, remove the snap-on plastic feet from the
bottom of the switch, as shown in Figure 36.
3. Turn the switch over.
4. Attach a rack-mount bracket to one side of the switch using six of the
screws that come with the switch and then install the second
rack-mount bracket on the other side of the switch with the six
remaining screws, as shown in Figure 37.
x610 Series Layer 3 Gigabit Ethernet Switches Installation Guide

Figure 36. Removing the Feet