Additional Rack Considerations; General Component Placement Guidelines - HP BL685c - ProLiant - 4 GB RAM Site Planning Manual

Hp bladesystem c-class site planning guide
Hide thumbs Also See for BL685c - ProLiant - 4 GB RAM:
Table of Contents

Advertisement

Additional rack considerations

Consider the following additional specifications and components, with regard to your specific rack
configuration:
Power—If a UPS is installed, do not exceed its output rating. Be sure to review the installation
instructions provided with each component for important cautions and warnings.
PDUs—Install PDUs before installing other components.
Height—The height of the rack and of rack-mountable components is measured in U increments,
where U = 4.5 cm (1.75 in). When you are configuring your rack installation, remember that the
total U measurement of the components you want to install cannot exceed the stated U height of the
rack.
Keyboard—The rack keyboard requires installation of a 1U keyboard drawer rack option kit.
Monitor—The monitor requires installation of a monitor/utility shelf rack option kit unless you are
using a rack-mountable flat-panel monitor.
Server console switch—If a console switch is configured, use the CPU-to-console switch cable
included with the server. The standard distance between the console switch and the keyboard,
monitor, and mouse can vary by 3-, 7-, 12-, 20-, and 40-ft lengths.
NOTE:
an appropriate cable, meeting fire-safety standards, must be used any time cabling is routed:
Through an overhead drop-ceiling
Under raised flooring
From room to room
From floor to floor
Be sure that the cable jacket or sleeving is made of material that does not burn easily and does
not exude toxic fumes when exposed to heat. Be sure that the cable you have selected is
appropriate for your installation site. If you require a U.S. plenum-rated (CL2P) cable, contact
your local HP authorized reseller to obtain any of the following options:
149363-B21-20-foot plenum cable
149364-B21-40-foot plenum cable
Rack baying option kits—The number of baying kits needed to join a series of racks is one less than
the number of racks in the suite. Each baying kit supplies parts to bay two cabinets on 600 mm (24
in) center line spacing.
Side panels—Only one set of side panels is required for each row of bayed racks.
Stabilizer kit—A stabilizer kit is either required or recommended, depending on your rack
configuration.

General component placement guidelines

WARNING:
stabilize the rack before extending a component outside the rack. Extend only one component
at a time. A rack may become unstable if more than one component is extended.
National electrical regulations governing the installation of building wiring require that
To reduce the risk of personal injury or damage to the equipment, adequately
Preparing for installation 60