PDU installation
The PDU can be installed in either a 1U or a 0U configuration. For specific details on installing the PDU in
the rack, see the installation instructions that came with the PDU
For technical specifications on HP Modular and Monitored PDUs, see the HP website
(http://h71028.www7.hp.com/ERC/downloads/4AA0-0689ENW.pdf).
IMPORTANT:
phase PDUs.
NOTE:
PDU. Do not exceed the rated current on circuit breakers.
c7000 PDU example
The following figure shows an example configuration of three c7000 enclosures connected to HP S348
(part number AF916A) PDUs. This specific wiring configuration is used to ensure that the load is evenly
balanced across all three phases of the incoming circuit, even with Dynamic Power Saver enabled.
Enclosure/switch
Switch C
Switch B
The three-phase c7000 enclosure cannot be connected to rack-based single-
Total VA load of the attached enclosures should not exceed the VA capacity of the
Power supply
PDU
Single
Left extension bar
Single
Right extension bar
Load segment
Port
2 = uppermost
1 = bottommost
Top
Top
Power requirements and considerations 43