10-2 Advanced problem solving procedures
Procedure
How to power up the DSNE network
Step
4
5
Enhanced network
Refer to procedure 10-2 to power up the ENET.
Procedure
How to power up the ENET
Step
1
2
3
297-1001-591 Standard 04.03 March 1999
10-1xxx
Action
Return to service (RTS) any links that you manually busied
in the power down process.
>LINKS <pair>
>RTS <plane> <links>
(The network is back in service [InSv]).
Continue this process until all of the network planes are
back InSv.
10-2xxx
Action
Make sure that all four power converter cards that you
power up sit correctly in the slots. The four power
converters consist of:
two +5V 80A Power Converter cards (NT9X30)
two –5V 20A Power Converter cards (NT9X31)
To turn ON the four power converters, press upward on
each power switch. The switch automatically returns to the
center position. As you turn ON each card, the
light-emitting diode (LED) of the converter turns off.
After you power up the shelf, you can load the shelf again
and RTS the shelf.
(continued)
—end—