PROCEDURE BEFORE STARTING DATA LINK

7.2 Module Installation Procedure

The following describes the procedure from the module installation to the operation check
of the safety master module.
(1) Install the modules
Install the safety power supply module, safety CPU module and safety master
module on the safety main base unit. Fix the modules with screws to prevent
them from being dropped, short-circuit and erroneous operation.
( Refer to Section 7.3.)
(Refer to Section 7.3.)
(2) Install remote modules
Install remote modules, such as safety remote I/O modules or safety remote
device modules, to a control panel or a machine. For how to install remote
modules, refer to the manual of each module.
(3) Wiring (power supply, I/O)
Connect the safety power supply module and the remote modules to power
supply. Also connect I/O wiring for the remote modules. For the wiring method,
refer to the manual of each module.
(4) Check before power-on
Check the power supply wiring and power supply voltage for the safety power
supply module and the remote modules. Also check that the
RUN/STOP/RESET switch on the safety CPU module is set to STOP.
(5) Check operation of the safety master module
Turn on the safety power supply module and conduct a hardware test to the
safety master module, and check the operation of the safety master module.
( Refer to Section 7.5.)
(Refer to Section 7.5.)
Start
End
7.2 Module Installation Procedure
1
2
3
4
5
6
7
8
7
- 2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Melsec-qs0j61bt12

Table of Contents