Installation; Tower Preparation - Harmar Mobility VPL400-X Installation & Service Manual

Vertical platform lift
Hide thumbs Also See for VPL400-X:
Table of Contents

Advertisement

VPL400-X: SECTION 4

INSTALLATION

SECTION 4
INSTALLATION

TOWER PREPARATION

1. Remove 5X front screws.
2. Remove the top cap by loosening the four (4)
side screws. See Figures 4-1.
3. Remove the front panel by rotating it out
slightly and lifting it out of the lower slots.
See Figure 4-2.
VPL400-X:
Install Manual
12
21JULY2023 | 630-00159 B
Figure 4-1
Figure 4-2
4. Position the VPL tower close to the upper
landing and stand it up using appropriate
material handling processes.
NOTE: Tower frame should only be lifted by the
rectangular tubes below the top plate.
5. Remove and discard the temporary bolt and
nut (5/16" hex) that secures the tensioning
pulley to the carriage for shipping. This bolt is
indicated with a red tag. Suspend the pulley
assembly behind the carriage.
See Figures 4-3 and 4-4.
Figure 4-3
Figure 4-4

Advertisement

Table of Contents