Finishing The Outdoor Unit Installation; To Check The Insulation Resistance Of The Compressor; To Finish The Outdoor Unit Installation - Daikin ERLA14D V3 Series Installer's Reference Manual

Hide thumbs Also See for ERLA14D V3 Series:
Table of Contents

Advertisement

10
|

Finishing the outdoor unit installation

10 Finishing the outdoor unit installation

10.1 To check the insulation resistance of the compressor

10.2 To finish the outdoor unit installation

Installer reference guide
156
NOTICE
If, after installation, refrigerant accumulates in the compressor, the insulation
resistance over the poles can drop, but if it is at least 1 MΩ, then the unit will not
break down.
Use a 500 V mega-tester when measuring insulation.
Do NOT use a mega-tester for low voltage circuits.
1 Measure the insulation resistance over the poles.
If
≥1 MΩ
Insulation resistance is OK. This procedure is finished.
<1 MΩ
Insulation resistance is not OK. Go to the next step.
2 Turn ON the power and leave it on for 6 hours.
Result: The compressor will heat up and evaporate any refrigerant in the
compressor.
3 Measure the insulation resistance again.
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.
INFORMATION
For the requirements of the refrigerant piping insulation, see
piping
insulation" [
1 Insulate and fix the refrigerant piping and cables as follows:
e
b
d
a Liquid pipe
b Gas pipe
c Finishing tape
d Interconnection cable (F1/F2)
e Insulation
2 Install the service cover.
Then
4
 93].
a
c
"8.1.2  Refrigerant
ERLA11~16D + EBSH/X(B)11+16P30+50D
Daikin Altherma 3 R ECH₂O
4P663482-1C – 2023.05

Advertisement

Table of Contents
loading

Table of Contents