Installation - Danfoss ASV-PV DN 15 Installation Manual

Hide thumbs Also See for ASV-PV DN 15:
Table of Contents

Advertisement

Available languages
  • EN

Available languages

  • ENGLISH, page 1
Installation Guide
ENGLISH
Automatic balancing valves ASV-PV is used
together with shut-o and measuring valve
ASV-M to control the di erential pressure
in risers where the radiator valves have
presetting facilities. ASV-PV is also used
together with adjustment valve ASV-I to
control the di erential pressure and ow
in risers where the radiator valves have no
presetting facilities (P/Q control), g. ❶.
ASV-PV maintains constant di erential
pressure across the riser.
Max. working pressure ...........................16 bar
Di erential pressure across valve:
DN 15 - 40 ...........................................10-150 kPa
DN 50 .................................................. 10-250 kPa
Max. ow temperature............................120 °C
Internal
Valve size
thread
DN 15
Rp ½
DN 20
Rp ¾
DN 25
Rp 1
DN 32
Rp 1¼
DN 40
Rp 1½
DN 50
-
Impulse line: G 1⁄16

Installation

ASV-PV must be installed in the return
pipe. The ow must be in the direction of
the arrow on the valve body g. ❸.
It is recommended that an FV lter be
installed in the system supply pipe. The
impulse tube must be tted on the ow
pipe, e.g. via an ASV-I or an ASV-M valve.
The tube must be ushed through before
being tted on the + connection of the
ASV-PV automatic balancing valves g. ❷.
ASV-PV must in addition be installed as
determined by installation conditions.
When the system has been in use for
some time, the connections with external
threads should be tightened once again to
minimize the risk for leakage.
Shut-o
Turning the ASV-PV knob fully clockwise
will shut-o the riser g. ❷ ①.
Pressure testing
Max. test pressure ....................................25 bar
Notes:
When pressure testing you must secure that
both sides of the membrane have the same
static pressure. That means the impulse
tube must be connected and any needle
valves must be open. If ASV-PV is installed
in combination with ASV-M both valves can
be open or closed (both valves must be in
4
SMT/SI
ASV-PV (DN 15-50)
the same position!). If ASV-PV is installed in
combination with ASV-I both valves must
be open. During this operation (closing or
opening the valves) please make sure that
there is never lower pressure on upper side of
the membrane.
If ASV- PV is installed in combination with
ASV-I do not drain main pipes while leaving
risers under pressure / lled with water. Doing
so ASV-PV membrane would have lower
pressure on upper side which might damage
the membrane.
If this instructions are ignored, the
membrane of the automatic balancing valve
might be damaged.
Setting/adjustment
External
thread
The ASV-PV valves are sold in four di erent
G ¾ A
∆p setting ranges. The valves are factory–
G 1 A
set to a de ned value as described on
Factory presseting table on g. ❾. Use
G 1¼ A
the following procedure to set the desired
G 1½ A
di erential presure: the setting on ASV-PV
G 1¾ A
can be changed by turning the setting
G 2½
spindle g. ❷②.
Turning the spindle clockwise increases
the setting; turning it counter clockwise
reduces the setting.
If the setting is not known, turn the spindle
fully clockwise. With this the setting on
ASV-PV is at maximum value within setting
range. Now turn the spindle a number of
times (n) as described in g. ❾ until the
required di erential pressure setting is
obtained.
Note:
Do not turn the spindle more than 20 turns as
it will become disengaged.
The connection (closed, g. ❹–① - open,
g. ❹–②) can be used for water tapping
and lling.
Starting
You can ll the system with the drain-
connection on ASV-PV. The system shall
be ventilated at the highest point. During
system start – opening the shut-o on
ASV-PV and partner valve - please secure
that there is the same static pressure on
both sides or higher pressure on upper
side of the membrane (+ connection,
Fig.❷). If lling is done by opening ASV-PV
and partner valve, please make sure there
is a pressure on the upper side of the
membrane by opening partner valve rst
before ASV-PV is opened.
VI.A6.D2.1T
Notes!
a) ASV-PV used with ASV-M (Fig. ❻):
if this procedure is not followed, the
membrane of ASV-PV might be damaged.
b) ASV-PV used with ASV/I (Fig. ❼):
If this procedure is not followed, ASV-PV
may become locked in closed position
even if the valve is fully opened.
c) Both ASV-PV and ASV-M/I should be
always fully opened if used together with
dedicated shut-o valves (Fig. ❽).
Fault location
Check the following if the riser valve does
not function correctly:
1. Is the ow direction through the valve
correct?
2. Is the impulse tube tted correctly and
are any needle valves open?
3. Is the valve shut-o open?
Insulation (DN 15 - 40)
The styropor packaging in which the valve
is supplied can be used as an insulation
jacket for temperatures up to 80 °C.