Manual battery full test
The manual battery test is run immediately, even if the UPS is operating in ABM mode, and no test is postponed or scheduled
to run in float mode.
ABM mode—the ABM cycle is stopped, the test is performed, and then the ABM cycle is restarted after the test is
complete.
Constant charge mode—The charging phase is restarted after the test is complete.

Starting power to the load

Start power to the load by placing the UPS in Operate mode.
IMPORTANT: AC power must be available the first time the UPS is started.

Installing the ERM

Before installing the ERM, review and observe all warnings in Precautions.
WARNING: A risk of personal injury or damage to the equipment exists. Uneven loading of equipment in the rack might
cause the rack to become unstable. Install the heavier components first, and then continue to populate the rack from the
bottom to the top.
Procedure
1. Install the mounting rails.
2. With one person on each side of the carton, lift the chassis and lower it to the floor in front of the rack.
3. Install the mounting ears on the chassis using the screws provided.
4. With one person on each side, lift the chassis to rail level and slide the chassis on the mounting rails.
5. Attach the chassis to the rack using the supplied screws.
26
Installation

Advertisement

Table of Contents