Check Before Power-On

No. Check Item
Equipment
1
appearance
Cable
2
appearance
3
Cable connection
4
Cable routing
Battery pack
5
copper bar
6
Switch
8

System Power-On

8.1

Installing the PSU

1. Push the locking latch leftward.
2. Pull out the handle.
3. Gently push the PSU into its slot along the guide rails.
4. Push the handle upward.
5. Push the locking latch rightward to lock the handle.
Expected Result
The equipment is intact and free from rust or paint flake-off. If the
paint flakes off, repair the damaged paint.
The labels on the equipment are clear. Damaged labels must be
replaced.
Cable sheathings are properly wrapped and not damaged.
Cable hoses are intact.
Cables are connected in the designed positions.
Terminals are prepared as required and securely connected.
Labels on both ends of each cable are clear and specific, and
attached in the same direction.
Electrical and ELV cables are routed separately.
Cables are neat and tidy.
Cable tie joints are evenly cut without burrs.
Cables are placed properly and with slack at bending points to
avoid stress.
Cables are routed neatly without twists or crossovers in the cabinet.
The copper bar is not deformed, and the plastic dip coating is not
damaged.
The DC LV Panel switch is set to OFF.
The battery rack switch is set to OFF.