Installing Rack Controller Cables
6.4
1. Remove the decorative cover and maintenance compartment cover from the rack controller
using the delivered security Torx wrench.
2. Connect the preinstalled cables to the BAT/BUS ports. Magnetic rings are delivered with the
product and need to be bound after being installed.
The black magnetic ring is installed on the left side of the rack controller, and the green
magnetic ring is installed on the right side of the rack controller.
Do not remove the cover from an unused pagoda connector.
200 kWh Model
Cable Label (Left)
107-1F1:2>TA1:2BAT+
109-1Q1:4>TA1:2BAT-
Wiring Terminal
2BAT+
2BAT-
33
Cable Label (Right)
108-1Q2:1>TA1:1BUS+
111-1Q2:3>TA1:1BUS-
Wiring Terminal
1BUS+
1BUS-