8. PREPARING APPLIANCE FOR INSTALLATION

8. PREPARING APPLIANCE FOR INSTALLATION
1. Detach the burner unit from the convection box by removing two screws (See
figure 10). Lift the burner unit clear.
2. Fit the two "U" section seals to the bottom edges of the convection box side
flanges (See figure 11).
3. It is important that the grommet
supplied in the loose parts pack is
fitted to the hole in the rear of the
convection box.
4. For concealed connection only:
Pierce the grommet to allow the pipe to
pass through it. The grommet should
envelop the pipe. If the hole is larger
than the pipe, seal it with tape. Do not
pierce the grommet unless the supply
Figure 10. Burner attachment points
pipe is to pass through it.
6. The heat engine or fascia will have a canopy shield
supplied with it. Fit this to the convected air outlet of the
appliance using the three self tapping screws supplied.
The design of the canopy shield may differ from that
shown (See figure 12).
Figure 11. 'U' Seals
Figure 12. Fitting canopy shield