Shipment and on-site transport
3. Carefully lift the control valve. Check
whether the lifting equipment and acces-
sories can bear the weight.
4. Move the control valve at an even pace
to the site of installation.
5. Install the valve into the pipeline (see the
'Installation' section).
6. After installation in the pipeline, check
whether the flanges are bolted tight and
the valve in the pipeline holds.
7. Remove slings.
b) Version with welding ends
1. Attach one sling to each welding end of
the body and to the rigging equipment
(e.g. hook) of the crane or forklift (see
Fig. 4-1).
2. Secure the slings attached to the body
against slipping using a connector.
3. 700 cm² actuator area and larger: at-
tach another sling to the lashing point on
the actuator and to the rigging equip-
ment.
4. Carefully lift the control valve. Check
whether the lifting equipment and acces-
sories can bear the weight.
5. Move the control valve at an even pace
to the site of installation.
6. Install the valve into the pipeline (see the
'Installation' section).
7. After installation, check whether the weld
seams hold.
8. Remove slings.
4-4