Figure 3-13 Antiseismic kit mounting hole positions
Step 2 Secure two antiseismic kits to the front and rear of the cabinet using twelve
M5x16 screws and four M12 screws.
Figure 3-14 Securing the antiseismic kits to the cabinet
Step 3 Reinstall the rear panel.
Step 4 Adjust the cabinet position so that the expansion bolt holes are aligned with the
eight holes at the bottom of the cabinet.
Step 5 Secure the two antiseismic kits at the front and rear of the cabinet to the floor
using eight M12 expansion bolts, as shown in