Maintenance Summary - 2.000 Operating hours
CM080
- Inspection of water cooling equipment (option)
Orientation
Requirement
Procedure
Maintenance Instructions
MS24-6
DIM123EN - 26.04.2022
Carrying out the maintenance activities described below requires
special knowledge. For this reason, these maintenance activities
must only be carried out by staff that has received adequate training
by the machine manufacturer!
Continuous inspection, maintenance and servicing of the installed water cooling
equipment and related monitoring functions ensure trouble-free and efficient use of
the machine. Any occurring malfunctions are detected at an early stage so they can
be eliminated early before they result in damage to and long downtimes of the
machine.
For all work in connection with operating materials, the information in
the data sheets of the respective manufacturers and the information
in the document Notes on Operating Materials must be observed.
For inspection of the water cooling unit, the following equipment is required:
-
device descriptions of the water cooling equipment (manufacture description)
and the monitoring systems used.
-
servicing, testing and maintenance schedules/logs of the customer.
-
Use an ample supply of cleaning rags. - Avoid using cotton waste and
compressed air.
-
Various sizes of jaw and box wrenches, and Allen keys.
1. Review of the customer's service, inspection and maintenance schedules.
2. Check operating condition. Active – Inactive.
3. Check the supply lines of the system for leaks and/or damage.
4. Check water level in the tank, top up if necessary.
5. Check water filter and related sensors.
Alternatively, the following procedure can be used!
Clean water filter, and replace if necessary.
6. Check water flow monitoring.
7. Check water temperature and related sensors.