Commissioning - FLOWTECH Flowpress Mini Single Operation And Maintenance Manual

Digital pressurisation unit
Table of Contents

Advertisement

6 COMMISSIONING

6.11 Pre-commissioning checklist:
Before starting the commissioning process the following conditions must be met. If these conditions
are not adhered to, damage to the equipment, system and property may result.
Ensure the unit is sited in a frost free area, away from precipitation and water sprays/jets.
All necessary pipe/electrical connections should have been made to a satisfactory standard by a
qualified person.
The temperature and pressure at the point of connection are within the operating limits of the
pressurisation unit.
The heating/cooling system is fitted with a safety valve and expansion vessel sized appropriately.
6.12 In order for the pressurisation unit and heating/cooling system to function
correctly the following conditions must be met. If these conditions have not
been met, the commissioning process should not continue.
Ensure the system connection has been made into the heating/chiller system return header.
Ensure Non-return valves, pressure reducing valves or RPZ valves are NOT installed between the
pressurisation unit and the heating/cooling system.
The expansion vessel is pre-charged to the correct pressure (equal to initial system design
pressure).
6.13 Prior to commissioning, fill the heating/cooling system via a filling loop. The
Flowpress Mini is NOT designed to fill the system from empty, it is only intended to
top up the system after occasional water leakage.
Ensure the heating/cooling system is filled and pressurised to the required cold fill pressure, with
the water at approximately ambient temperature.
Ensure the system is dosed with a suitable corrosion inhibitor. Note the Flowpress Mini is not
designed for dosing chemicals into the system, this mustbe done via other means.
6.14 Expansion vessel setting:
To set or check the expansion vessel charge pressure the lock-shield valve between the
Flowpress Mini and the vessel must be closed and the vessel drained using the drain valve.
A suitable gauge should be used to check the charge pressure.
If the charge pressure is too high it can be reduced by releasing air from the vessel pre-charge
valve or by using a pressure gauge with an integral air release valve.
If the charge pressure is too low a small increase can be provided using a car foot pump
otherwise an oil free compressor or nitrogen bottle is recommended.
When the correct pressure is set the Schrader valve protective cap must be replaced.
Check the integrity of the pipe-work. Ensure the lock-shield valve between the system and the
expansion vessel is open and the drain valve is closed.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Flowpress Mini Single and is the answer not in the manual?

This manual is also suitable for:

Flowpress mini twin

Table of Contents