15. Secure the bridge unit [A] (! x 4 - M4x8).
16. Route the cables [B] through the openings [C].
17. Route the solenoid harness [D] through the opening [E].
18. Connect the cables to the solenoid and sensors and clamp the cable as shown.
19. Reinstall the rear cover and proof tray unit.
20. Install the mailbox on the main machine (refer to the Mailbox Installation
procedure for more detail).
If installing the 3000-sheet finisher (A697), do steps 21 to 25.
21. Install the front joint bracket [F] and rear joint bracket [G] which are contained in
the finisher's accessory box.