When raising the leveling feet, at least one person is required to hold the cabinet
to prevent it from sliding.
Figure 5-5 Raising the anchor bolts to the highest position
Step 6 Slowly move the cabinet over its castors to the installation position.
Step 7 Take out the desiccant.
----End
Lithium Battery Side Cabinet
Step 1 Use a pallet truck to transport the cabinet to the installation position.
Step 2 Remove the packing materials and put aside the accessories and marking-off
template.
Step 3 Check that the cabinet is intact.
1.
2.
----End
Issue 13 (2023-03-26)
NO TICE
Visually inspect the cabinet appearance for damage caused during
transportation. If any damage is founded, report the photos to the carrier
immediately.
Check that all fittings comply with the packing list. If there is any discrepancy,
keep a record and contact the supplier immediately.