Installation Manual – Hardware Installation
BBU3806 WCDMA Base Band Unit
Special tools
Instruments
4.4 Checking Installation Conditions
In conformance with Engineering Technical Specifications and Lightning Protection
and Grounding Specifications for Communications Equipment, the project supervisor
shall:
Check the construction conditions
Fill out the Installation Environment Checklist
Sign the Kickoff Agreement with the customer if all conditions are ready
Formulate the Project Installation Plan.
If the installation preparations of the customer are not ready as required, fill out the
Onsite Work Liaison Form and give the reason for delayed kickoff.
If the customer needs immediate kickoff, ask the customer to specify and promise the
exact time when the installation is ready for kickoff. For the project that is unable to be
improved or that does not meet the specified requirements, a memo has to be signed.
4.4.1 Site Construction Requirements
Check the installation site with respect to its floor space, height, load bearing capacity,
and groove layout. If the site cannot satisfy these requirements, the customer has to
reconstruct the site as required.
4.4.2 Environment Requirements
Check the environment as follows:
A non-conductive screwdriver
An antistatic wrist strap
A safety knife
A stripper for 75 Ω coaxial cables
A pair of connector crimping pliers for 75 Ω coaxial cables
A pair of multi-purpose crimping pliers
A pair of crimping pliers for network cables
A multi meter
A power meter
Portable computer
Huawei Technologies Proprietary
4-3
Chapter 4 Installation Preparations