Commissioning - Delta M100 210 Operation And Installation Manual

Grid-tie transformerless solar inverter
Hide thumbs Also See for M100 210:
Table of Contents

Advertisement

5.4 De-Commissioning
- Ensure DC and AC cables are always de-energized during De-commissioning
to avoid Shock Hazard!
- The surface of the inverter may be hot to cause injury, ensure the temperature
is in the proper range before De-commissioning.
The procedure of M100_210 de-commissioning:
1. Follow Section 5.1.1 to disconnect from the grid.
2. Follow Section 5.1.2 to open the door.
3. Remove communication, DC, AC and Internal PE cables from terminals.
- All cable conductors have to seal well with high insulation material.
4. Put stopper into the each hole of inner rubber and fasten well for sealing.
DANGER : ELECTRICAL HAZARD!!
CAUTION : HOT SURFACES
ATTENTION
71