Mechanical installation

The infrastructure of the electric room is finished and the installation site
1.
is sufficiently ventilated or cooled and dehumidification to ensure the
converter can running at the appropriate temperature and humidity.
2.
The wall behind the unit is of non-flammable material. Please take the
photo and send back.
3.
There is enough free space above the drive to enable cooling air flow,
service and maintenance. See layout drawing. Please take the photo and
send back.
4.
Ambient operating conditions meet the specifications given in chapter
Technical data
5.
Drive installed according to the instructions in this manual (Chapters
Mechanical installation
6.
Drive securely fastened to the floor
7.
The combination of INU cabinet and transformer cabinet is finished.
8.
The floor that the unit is installed on is of non-flammable material, as
smooth as possible, and strong enough to support the weight of the unit.
Check the floor flatness with a spirit level. The maximum allowed
deviation from the surface level is 5 mm in every 5 meters. Level the
installation site, if necessary, as the cabinet is not equipped with
adjustable feet.
9.
Fan units installed with correct poison and type.
1 0 .
Visual inspection:
no badly affixed or damaged components
no foreign objects inside cabinet
no dirt, dust and humidity inside cabinet

Electrical installation

1.
Types and cross-sections of control cables suitable for the signal type
and signal level
2.
Types and cross-sections of power cables selected according to the
ACS580MV Engineering Guideline
3.
Pulse encoder cable screens connected to screen grounding point and
not connected directly to the pulse encoder interface (only applicable for
drives with pulse encoder interface)
and
Electrical
installation)
(2UBB013672 [English])
Installation checklist 35