Installation - ABB ACS580MV Quick Manual

Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

14 Mechanical installation

Installation

1.
Lift the fan unit onto the cabinet roof by a forklift or a crane (if using a crane,
mount the lifting eyes at the top of the fan box).
~70 kg for EC500 fan units
~90 kg for EC560 fan units
NOTICE
The mounting position can be identified by the cutouts in the drive roof.
2. Use the supplied screws to fasten the fan units to the cabinet roof.
For information on the electrical installation, see
for fan units.
For 3.3 kV (Power ≤ 710 kW) and 4.16 kV (Power ≤ 870 kW), EC fans need to be
installed with fan box and air channel in the field.
 
Control and power supply cables