WARNING . . .
Do Not Use Machine
Until System Is
Working Properly
If all of these checks cannot be
verified, do not attempt to use the
MM-TA-12B System/guarded
machine until the defect or prob-
lem has been corrected (see
Section 5).
Attempts to use the guarded
machine under such conditions
could result in serious bodily
injury or death.
WARNING . . .
Before Applying
Power to the
Machine
Verify that the guarded area is
clear of personnel and unwanted
materials (such as tools) before
applying power to the guarded
machine.
Failure to do so could result in
serious bodily injury or death.
Buy: www.ValinOnline.com | Phone 844-385-3099 | Email: CustomerService@valin.com

6. Periodic Checkout Procedures

Study each procedure from beginning to end before you start to make sure that
you understand each step. Refer all questions to the Banner Applications
Engineering Department at the address or numbers listed on the front cover of
this manual. Checkouts must be performed as detailed in Section 6.1 below and
results should be recorded and kept in the appropriate place (e.g., near the
machine, and/or in a technical file).

6.1 Schedule of Checkouts

Initial Checkout: The procedure for initial checkout of the MM-TA-12B System is
described in Section 3.6. This procedure is performed at installation, and at any
time the System, the guarded machine, or any part of the application is installed
or altered. The procedure must be performed by a Qualified Person.
Commissioning Checkout: Should be performed after installation or whenever
changes are made to the system (either a new configuration of the MM-TA-12B
System or changes to the machine). The procedure must be performed by a
Qualified Person. See Section 6.2.
Daily Checkout: The procedure for "daily" checkout of the MM-TA-12B System is
to be performed at each shift change or machine setup change, whenever the
System is powered up, at least daily. The procedure may be performed by a
Designated Person or a Qualified Person. See Section 6.3.
Semi-Annual Checkout: The procedure for initial checkout of the MM-TA-12B
System is to be performed every six months, following installation of the System.
The procedure must be performed by a Qualified Person. See Section 6.4.

6.2 Commissioning Checkout

Perform this checkout procedure as part of Safeguarding System installation
(after the System has been interfaced to the guarded machine as described in
Sections 3.6 and 3.7), or whenever changes are made to the System (either a
new configuration of the Module, devices connected to it, or changes to the
machine). A Qualified Person (as defined in the Safety Glossary) must perform
the procedure; checkout results should be recorded and kept on or near the
guarded machine, per OSHA 1910.217(e)(1).
To prepare the MM-TA-12B Module for this checkout, ensure the configuration is
as it will be during machine operation.
Safeguarding Checkout
1) Examine the guarded machine to verify that it is of a type and design com-
patible with the safeguarding system that has been installed. See page 2.
2) Verify the system(s) checkout procedures for the external safety systems
connected to the MSSI and the USSI inputs as described by the appropriate
manuals. Do not proceed until all checkout procedures are completed suc-
cessfully and all problems have been corrected.