Electrical installation of the control box
5. Connect these wires:
•
•
6. Tighten the screws to the correct torque. For the specification, refer to section
20.5
15.4.2
Connect the DC auxiliary power output cables to the next control
box
Preliminary requirements
Procedure
1. Strip the insulation from the end of
the cable (A).
2. Strip the insulation from the ends
of the wires (B) and (C). For the
specification, refer to section
20.12.5.
3. Crimp ferrules onto the end of the
wires.
4. Loosen the screws on the terminals
(D) and (E).
5. Connect these wires:
•
•
6. Tighten the screws to the correct torque. For the specification, refer to section
20.5.
15.5
Connect the Ethernet cables to the control box
Preliminary requirements
66
0V DC wire (B) to the terminal X1-5 (D)
24V DC wire (C) to the terminal X1-3 (E)
.
1.
There is a next control box
in the daisy-chain
•
Torque screw driver
•
Wire cutter
•
Wire stripper pliers
•
Crimp pliers
0V DC wire (B) to the terminal
X1-6 (D)
24V DC wire (C) to the terminal
X1-4 (E)
•
Ethernet cable from the power cabinet. Refer to section
•
Ethernet cable to the next control box (optional). Refer to section
20.12.8
.
•
DC auxiliary cable. Refer to
20.12.5
section
.
•
Ferrules
•
C
E
D
20.12.8
6AGA000007-0611-EN | 001
A
B
.