If it is necessary to remove safety devices, immediately install the safety devices
after the work.
Put on the correct personal protective equipment. Refer to section
3.6

Safety instructions during transport

Preliminary requirements
Make sure that the hoisting equipment or forklift truck can lift the EVSE safely.
Take into account the mass and the center of gravity of the EVSE.
Obey the safety instructions that apply to the hoisting equipment or the forklift
truck.
Put on the correct personal protective equipment. Refer to section
3.7

Safety instructions for earthing

Preliminary requirements
Make sure that the EVSE is connected to an earthed, metal, permanent electrical
system. Alternatively, install an equipment-earthing conductor with circuit
conductors. Connect this earthing conductor to an equipment-earthing terminal
or lead on battery charger.
Make sure that the connections to the EVSE comply with all applicable local
rules.
3.8

Lightning protection

Make sure the EVSE is within the protection angle of the lightning distraction
according to NEN-EN-IEC 62305. Install an earthing rod in the earth near the
foundation of the power cabinet.